Caroona Coal Project
- Ownership: 100 per cent
- Products: Thermal coal
- Location: New South Wales, Australia
In April 2006, the NSW Minister for Mineral Resources awarded the coal exploration licence (PDF 2.0KB) for the Caroona area to BHP Billiton. An exploration licence provides the BHP Billiton Caroona Coal Project team the opportunity to investigate the viability of coal mining within the exploration licence area. See the Location Map. Find out about our Community Fund.
Key activities included during initial investigations (concept studies) will be:
- Community and stakeholder consultation
- Planning and conducting regional exploration within the exploration licence area to determine the extent of coal resources
- Conducting environmental assessments to understand the local environment such as water and noise, flora and fauna and cultural heritage
- Identifying areas within the licence area for more detailed exploration and assessment
The Caroona Coal Project is in its very early stages, and the project team anticipate that studies will take between four and five years to complete. As the project team learns more about the area and potential changes, information will be distributed to the local community and other stakeholders.
The Exploration Licence Area
The Caroona Coal Exploration area is located about 50km Southeast of Gunnedah and 30km Northwest of Quirindi. The area covered by the exploration licence is approximately 350km2 and comprises part of the Department of Primary Industries held Authorisation 216.
The Kamilaroi Highway between Gunnedah and Quirindi passes through the eastern part of the exploration licence area, and the Werris Creek-Binnaway Branch railway passes from east to west through the centre of the area. See Exploration Map (PDF 136 KB)
Project Phase
The Caroona Coal Project is in its very early stages. Initial landowner meetings have begun. The project team hope to complete all meetings before the start of any exploration activities.
Environment & Community/Social Information
The Caroona Project is committed to BHP Billiton's health, safety, environment and community Sustainable Development Policy, Standards and Guidelines.
BHP Billiton is committed to an open and informative consultation process, and encourages all community members to be involved in the community consultation and participation activities.
Initial stages of the consultation have begun and have included discussions with landowners within and around the Exploration Licence area, Walhallow Aboriginal Community, Liverpool Plains Shire Council, Gunnedah Shire Council, and State and Federal Representatives. Consultation has focussed on:
- Discussing the scope of works involved in the exploration and preliminary assessment phase
- Building community understanding of BHP Billiton and the approval process
- Gathering information from land owners, key stakeholders, and the broader community
Downloads
- Project Update October 2008 (PDF 3 MB)
- Gunnedah Coal Conference Presentation August 2008 (PDF 2.5 MB)
- Interim Report to Stakeholders August 2008 (PDF 1 MB) News Release Interim Report (34 KB)
- Project Update June 2008 (PDF 2 MB)
- Review of Environmental Factors for Caroona Exploration Program Seismic Survey (PDF 1.9 MB)
- Review of Environmental Factors for Caroona Exploration Program Reconnaissance Drilling and Associated Activities 2007 to 2011 (PDF 1 MB)
- Project Update April 2008 (PDF 2 MB)
- Project Update October 2007 (PDF 2.2 MB)
- Community Presentation (PDF 1.7 MB)
- Project Update June 2007 (PDF 2 MB)
- Project Update April 2007 (PDF 2 MB)
- Project Update January 2007 (PDF 1 MB)
- Review of Environmental Factors for Stage 1 of Caroona Exploration Program - October 2006 (PDF 1.5 MB)
- Review of Environmental Factors for Exploration Borehole C44 Caroona - August 2006 (PDF 727 KB)
- Project Update July 2006 (PDF 459 KB)
- Project Update March 2006 (PDF 2.2 MB)
- Exploration Environmental Management Plan (PDF 2 MB)
Presentations Given To Consultative Committee
- Environmental Assessment Approach (PDF 283 KB)
- Groundwater and Exploration Techiques (PDF 633 KB)
- Exploration Environmental Management Plan Presentation (PDF 4.2 MB)
Community Consultative Committee
A Community Consultative Committee for the Caroona Coal Project has been established to provide a forum to address community concerns and to enable an open communication process between the community and the Caroona Coal Project team during the exploration period.
For further information on the consultative committee please contact:
Garry West
Phone: (61 2) 6362 5646
Fax: (61 2) 6362 7522
Links
Contact Details
Further information on the Caroona Coal Project can be obtained by contacting:
Stephen David
General Manager Caroona Coal Project
Phone: 1800 216 266
Email: CaroonaCoalProject@BHPBilliton.com